Mid-County Mini Transfer & Recycling Facility Roadway Reconfiguration and Truck Entrance
Last Updated: 08/14/2026 Category: Roadway Current Phase: Design Development
The design, permitting, and construction of a new gated access trucking road into the mini-transfer station.Midway Boulevard Sidewalk (HB41)
Last Updated: 08/17/2026 Category: Sidewalks Current Phase: Planning and Project Approval
Midway Boulevard sidewalk and pedestrian bridge.Last Updated: 08/12/2026 Category: Parks And Recreation Current Phase: Construction
Creation of a master plan through the park design process and phase 1 development.Northwest Port Charlotte Maintenance Dredging - Exterior
Last Updated: 08/14/2026 Category: Coastal Current Phase: Planning and Project Approval
Design, permitting, and dredging of the exterior parts of the access channels, and the interior parts of the mouths of the Apollo, Venus and Cheshire channels for the Northwest Port Charlotte Waterway MSBU. The project may also include the Juno Waterway.
Northwest Port Charlotte MSBU Bridge Rehabilitations
Last Updated: 08/14/2026 Category: Bridges Current Phase: Construction
Northwest Port Charlotte MSBU Bridge Rehabilitations - #014044 and #014045NWPC Bridge Rehabilitation Chamberlain over Cheshire Waterway Project
Last Updated: 08/14/2026 Category: Bridges Current Phase: Design Development
NWPC Bridge Rehabilitation Chamberlain over Cheshire Waterway ProjectOld Landfill Road Safety Improvements
Last Updated: 08/14/2026 Category: Roadway Current Phase: Design Development
Old Landfill Rd safety improvements.Last Updated: 08/14/2026 Current Phase: Construction
Replacement of boardwalk at Oyster Creek Environmental Park.Last Updated: 08/17/2026 Category: Drainage Current Phase: Design Development
Removal and disposal of all nuisance and exotic vegetation and trash from approximately 18.65 acres of Oyster Creek.