Project Description

This project includes procuring an engineering firm to design the necessary structural repairs, followed by contracting with a construction firm to carry out the rehabilitation work. This project for the Northwest Port Charlotte MSBU includes two bridges -  

Bridge #014044 Chamberlain Boulevard over Jupiter Waterway.

Bridge #014045 Chamberlain Boulevard over Apollo Waterway.

Project Location

Bridge #014044 Chamberlain Boulevard over Jupiter Waterway.

Bridge #014045 Chamberlain Boulevard over Apollo Waterway.

Latest Updates

Project Activity - May 2026

Bids were opened on March 18, 2026, with Zep Construction identified as the lowest responsive bidder at $1,870,145.46. The contract was approved by the Board of County Commissioners on April 14, 2026, after which Purchasing will schedule the Pre‑Construction Meeting.

Budget

Phase Cost
Design $197,560
Construction $1,870,145.46
Funding source(s): Northwest Port Charlotte MSBU

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Design Development 01/29/2024 10/03/2025 12/17/2025

Project Phase
Construction

Last Updated
05/13/2026

Project Manager
Kelly Slaughter

Public Relations
Chad Ray
Email Public Relations

Project Number
2024001656

Sponsor Department
Public Works

Design Engineer/Architect
DRMP Engineering

Construction Contractor
Zep Construction