Project Description
This project includes procuring an engineering firm to design the necessary repairs, followed by contracting with a construction firm to carry out the rehabilitation work. The project includes joint repairs, pile jacket repairs, guardrail repairs, milling asphalt, and repaving. This project for the South Gulf Cove MSBU has three (3) bridges scheduled for repairs.
St. Paul Boulevard over Zephyr Waterway - Bridge #014065
San Domingo Boulevard over Santa Cruz Waterway - Bridge #014070
Ingraham Boulevard over Santa Cruz Waterway - Bridge #014072
Project Location
St. Paul Boulevard over Zephyr Waterway - Bridge #014065
San Domingo Boulevard over Santa Cruz Waterway - Bridge #014070
Ingraham Boulevard over Santa Cruz Waterway - Bridge #014072
Latest Updates
Project Activities – June 2026
Construction on the Ingraham Bridge over the Santa Cruz Waterway (Project 014072) will be completed and opened on June 19, 2026.
Bridge Closure on San Domingo Bridge over the Santa Cruz Waterway will start on June 19, 2026, through July 22, 2026.
Budget
| Phase | Cost |
|---|---|
| Design | $128,960 |
| Construction | $1,195,628.70 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 03/29/2024 | 04/14/2025 | 05/06/2025 |
| Construction | 04/06/2026 | 08/04/2026 |
Project Phase
Construction
Last Updated
06/17/2026
Project Manager
Kelly Slaughter
Public Relations
Chad Ray
Email Public Relations
Project Number
2024001528
Sponsor Department
Public Works Engineering
Design Engineer/Architect
DRMP Engineering
Construction Contractor
Structural Technologies, LLC