Project Description
The existing pool at Port Charlotte Beach Park will be replaced with a community pool suitable for lap swimming, aerobic exercise, therapy, and other special events.
The proposed pool will be 54% larger than the existing pool (140,000 vs. 65,000 gallons) and include lap lanes. The facility will have a check-in station, locker rooms, multiple restrooms, office space, a break room, storage areas, and restrooms for the pier.
Project Location
4500 Harbor Blvd. Port Charlotte, FL 33952Project Impacts
Power and water have been rerouted to the sailing center building. All permits have now been issued and earthwork has begun with cast piles and site grading on track.
">All CIP walls and interior masonry walls have been completed. Roof trusses and deck are completed. Roof dry in is in progress. Interior framing and insulation in progress. MEPF rough-in is in progress. The pool structure is complete with the walls and slab poured. Backfill and plumbing/electrical for the pool will follow. Access control cabling has been run. ]Latest Updates
All CIP walls and interior masonry walls have been completed. Roof trusses and deck are completed. Roof dry in is in progress. Interior framing and insulation in progress. MEPF rough-in is in progress. The pool structure is complete with the walls and slab poured. Backfill and plumbing/electrical for the pool will follow. Access control cabling has been run.
Budget
| Phase | Cost |
|---|---|
| Design | $262,000.00 |
| Construction | $7,938,000 |
| Total Budget | $8,200,000.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 10/01/2022 | 10/01/2022 | 10/01/2022 |
| Design Development | 11/29/2024 | 08/29/2025 | 09/10/2025 |
| Construction | 08/29/2025 | 12/24/2026 | |
| Turnover & Closeout | 12/30/2026 | 01/29/2027 |
Supporting Materials
Project Phase
Construction
Last Updated
04/01/2026
Project Manager
Trevor Cole
Public Relations
Brian Gleason
Email Public Relations
Project Number
c722104
Sponsor Department
Community Services
Design Engineer/Architect
Harvard Jolly
Construction Contractor
Tandem Construction