Project Description
Multiple boardwalks and piers have sustained extensive damage, including deck boards, stanchions, support beams, piles, handrails, caps, bolts, hurricane straps, and pickets. Additional site damages include three parking lot bollards and 10 trash/recycling containers.
Public Relations:
Project Managers:
- Lonne Moore
Project Location
2333 Placida Road, Englewood, FL 34224Latest Updates
| Description of Work | Estimated Start | Estimated Completion | Storm Event |
|---|---|---|---|
|
Fencing |
|||
|
Park amenities |
|||
|
Sidewalks, boardwalks, piers, dock |
10/28/2025 | 5/1/2026 | Ian |
Budget
| Phase | Cost |
|---|---|
| Total Budget | $378,000.00 |
Last Updated
01/29/2026