Project Description
Replacement of the existing aging slab and installation of multiple new pieces of equipment.Project Location
Carmalita Park
Capt. Don Cerbone Skate Park
2605 Carmalita St.
Punta Gorda, FL 33950
Project Impacts
The closure of the skate park will begin the week of November 2, 2026 and will continue for apx. 8 weeks.Budget
| Phase | Cost |
|---|---|
| Construction | $223,924.92 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Construction | 11/02/2026 | 12/31/2026 |
Project Phase
Construction
Last Updated
10/09/2026
Project Manager
Lacey Solomon
Public Relations
Breanna Benevenga
Email Public Relations
Sponsor Department
Community Services