Darst Park Shoreline and Boarding Pier Repairs
Last Updated: 08/28/2026 Category: Parks And Recreation Current Phase: Design Development
Darst Park Shoreline and Boarding Pier RepairsLast Updated: 08/28/2026 Category: County Facilities Category: Sales Tax Funded Current Phase: Construction
Construct a new fire station at a location to be determinded, replacing the old fire station. New fire station will generally conform to a new prototype design for new and replacement stations. Includes land acquisition for station to be located nearby present location.
Placida West Boat Ramp Expansion
Last Updated: 08/28/2026 Category: Parks And Recreation Category: Sales Tax Funded Current Phase: Design Development
A 2014 Tier 2 Sales Tax project. The Placida Boat Ramp West Expansion project develops the property adjacent to the existing boat ramp to add features including a new two-lane boat ramp, kayak launch, restroom, and parking.Port Charlotte Beach Park Shoreline Stabilization
Last Updated: 08/28/2026 Category: Coastal Category: Parks And Recreation Current Phase: Design Development
Port Charlotte Beach Park Shoreline Stabilization
South County Annex Replacement
Last Updated: 08/28/2026 Category: County Facilities Category: Sales Tax Funded Current Phase: Design Development
The current Annex has reached the end of life, and stands in a high risk flood zone. The project will include master planning the current and future needs of stakeholders as well as site feasibility to determine the best location for a new building. The primary function of the South County Annex is to serve the regional community with governement services that include the Tax Collector, Property Appraiser, Supervisor of Elections and Board of County Commissioners.Burnt Store Water Reclamation Facility Expansion
Last Updated: 08/24/2026 Category: Utilities Current Phase: Design Development
This expansion project will increase wastewater treatment capacity for the Burnt Store service area.East Port Water Reclamation Facility Expansion
Last Updated: 08/24/2026 Category: Utilities Current Phase: Construction
This project includes the expansion of the current water reclamation facility to treat six million gallons of wastewater per day to nine million gallons per day. The project also includes advanced wastewater treatment, which is a valuable addition to the treatment process to ensure treated water has as low concentrations of nutrients as possible.Hillsborough Boulevard Water Main Project
Last Updated: 08/24/2026 Category: Utilities Current Phase: Construction
This project will install an eight-inch water main along Hillsborough Boulevard from Yorkshire Street to U.S. 41. The water main will be installed parallel to the Peace River Manasota Water Authority’s 42-inch Phase 2B Pipeline.
Lakeview/Midway Wastewater Expansion
Last Updated: 08/24/2026 Category: Utilities Current Phase: Design Development
This project proposes construction of a wastewater collection system to service properties with sewer service, new water service lines and a vacuum station that will provide sewer collection for the wastewater system.