Project Description
The existing pool at Port Charlotte Beach Park will be replaced with a community pool suitable for lap swimming, aerobic exercise, therapy, and other special events.
The proposed pool will be 54% larger than the existing pool (140,000 vs. 65,000 gallons) and include lap lanes. The facility will have a check-in station, locker rooms, multiple restrooms, office space, a break room, storage areas, and restrooms for the pier.
Project Location
4500 Harbor Blvd. Port Charlotte, FL 33952Project Impacts
Power and water have been rerouted to the sailing center building. All permits have now been issued and earthwork has begun with cast piles and site grading on track.
">Latest Updates
At the Pool, pool filling is complete and chemical balancing is in progress. Starting blocks and the accessible lift have been installed, with equipment commissioning currently underway. At the Pool Equipment Building, mechanical, electrical, plumbing, and fire protection trim-out is nearing completion, and interior doors have been installed. Equipment commissioning remains in progress, with final mechanical, electrical, plumbing, and fire protection inspections and the final coat of paint to follow. At the Pool House, mechanical, electrical, plumbing, and fire protection trim-out is nearing completion, and interior doors and casework have been installed. Audio-visual equipment installation is in progress, and Musco lighting commissioning is complete. Final mechanical, electrical, plumbing, and fire protection inspections and the final coat of paint will follow.
Budget
| Phase | Cost |
|---|---|
| Design | $262,000.00 |
| Construction | $7,938,000 |
| Total Budget | $8,200,000.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 10/01/2022 | 10/01/2022 | 10/01/2022 |
| Design Development | 11/29/2024 | 08/29/2025 | 09/10/2025 |
| Construction | 08/29/2025 | 12/24/2026 | |
| Turnover & Closeout | 12/30/2026 | 01/29/2027 |
Supporting Materials
Project Phase
Construction
Last Updated
09/11/2026
Project Manager
Trevor Cole
Public Relations
Brian Gleason
Email Public Relations
Project Number
c722104
Sponsor Department
Community Services
Design Engineer/Architect
Harvard Jolly
Construction Contractor
Tandem Construction